How should contractors handle CL monuments in wells when rehabilitating streets?
Posted: Fri Sep 29, 2023 7:28 am
How do contractors handle CL monuments in wells when rehabilitating streets?
Besides having an LS do Pre and Post CRs
Like a water valve?
The water valve hand well and cover is lowered below the pavement section as one of the 1st steps of rehabilitating the street ("lowering iron").
After the new pavement is installed, the water valve hand well and cover is raised to the new pavement surface ("raising iron").
What if the top of the monument in the well is above the new pavement section?
How should contractors handle CL monuments in wells when rehabilitating streets?
Besides having an LS do Pre and Post CRs
Like a water valve?
The water valve hand well and cover is lowered below the pavement section as one of the 1st steps of rehabilitating the street ("lowering iron").
After the new pavement is installed, the water valve hand well and cover is raised to the new pavement surface ("raising iron").
What if the top of the monument in the well is above the new pavement section?
How should contractors handle CL monuments in wells when rehabilitating streets?