City - County dispute
Posted: Mon Jan 19, 2026 1:48 pm
I have an unusual predicament. The parcel is the SW 1/4 of the SW 1/4 of Section 24. The north half of the parcel is within the County of S.L.O. and the South portion is within the City of S.L.O. Over the years, the County issued numerous development permits calling out ONLY the portion of the parcel within the County jurisdiction. So, under SMA 66499.35(c) we applied for a certificate of compliance through the County and they issued the certificate for only the north portion in 2025.
The City is now refusing to issue a cert. on the remaining portion of the property, since they never issued permits for the portion within the City. So, how only half the parent parcel is a legal lot.
What is the remedy?
1) Conditional cert. within the city?
2) Parcel map with just one parcel within the City's jurisdiction?
3) Parcel map with two parcels processed through both agencies?
thanks
The City is now refusing to issue a cert. on the remaining portion of the property, since they never issued permits for the portion within the City. So, how only half the parent parcel is a legal lot.
What is the remedy?
1) Conditional cert. within the city?
2) Parcel map with just one parcel within the City's jurisdiction?
3) Parcel map with two parcels processed through both agencies?
thanks