tentative map requirements for remainder parcels

Post Reply
MikeT
Posts: 106
Joined: Tue Jun 02, 2015 11:28 am

tentative map requirements for remainder parcels

Post by MikeT »

Hello.

Has it been generally accepted by planning departments to only show contouring for the parcel to be carved out and
not the remainder parcel? For example, if you're carving out a 1-2 acre parcel out of a heavily forested and steep 10 acre parcel, will
planning departments accept just showing contouring on the 1-2 acre parcel only?

Thanks in advance for any input.

Mike
Man of Chain
Posts: 46
Joined: Thu Apr 12, 2018 2:33 pm

Re: tentative map requirements for remainder parcels

Post by Man of Chain »

They have for me when I discussed the challenges to them before moving ahead and just submitting it. Another option is to import a DEM from the quadrangle in the area and disclaim it. Again I would try to pre-confirm that planning will not reject it.
mpallamary
Posts: 3466
Joined: Tue Mar 11, 2008 2:12 pm

Re: tentative map requirements for remainder parcels

Post by mpallamary »

Planners are not surveyors. Ask to review it with the individual in "responsible charge" for their land surveying.